This picture shows an existing movable bar. The wall that appears to be a wall with the 2 oriental hats hanging on it is actually fabric stabled and sewed together on a 2 by 4 board nailed to the joist above. Behind the bar, where the window is fabric needled in position to secure the material in front of the insulation. The entire basement (walls and ceilings) was done this way, Genius in my opi
In this area the designed is to build a bathroom (toilet and sink) and beside it a wet bar. Your looking at the fabric and on the floor a rough in plumbing.
Removing the the 2 by 4s and fabric to start the process by laying out the plans on the floor.
Laying down the 2 by 4 pressure treated wood per blue print, upper left side is where to toilet will be.
Using 3 inch lead anchor to secure the bottom plate to the floor.
Add Caption
Continuing laying out the bottom plate for the bar.
Installing the studs that will be the walls for the bathroom and the wet bar.
The stud walls view of the outside bathroom and outside wet bar.
The stud walls view of the bathroom.
Add Caption
This is a continuation building a wall for the laundry room and adding a electrical plug with updated lighting in to be a hallway and laundry room.
Add Caption
Running electrical wiring for plugs, lighting, for the wet bar, the bathroom and the laundry room.
Continuing running electrical wiring throughout the project (plugs , switches, lighting)
Starting with installing 1/2 inch drywall outside the laundry room.
Add Caption
Continuing installing drywall on the outside of the bathroom and both side of the bar walls.
Add Caption
Add Caption
Add Caption
Add Caption
Add Caption
Add Caption
Inside look of the 1/2 inch drywall installation having to before finishing the electrical.
Add Caption
Drywall work and electrical work is being performed.
Add Caption
Add Caption
Add Caption
Add Caption
Add Caption
Make a countertop ready for tiling.
Add Caption
Add Caption
Add Caption
Add Caption
Add Caption
Add Caption
Add Caption
80 CFM Exhaust fan installation for the bathroom.
Add Caption
2 dedicated circuits were ran for the bar and bathroom receptacles and hall and main room, there were no plugs.
Add Caption
Add Caption
Add Caption
Add Caption
Add Caption
Add Caption
Add Caption
Add Caption
THIRI: The Home Improvement Remodelers INC.
We use cookies to analyze website traffic and optimize your website experience. By accepting our use of cookies, your data will be aggregated with all other user data.